Performance

Business Performance

5 Thermal Power Generation Companies
5 Thermal Power Generation Companies
Korea South-East Power Co., Ltd. Yeongheung Power Plant
  • · Performed maintenance on ST LPBP Body Seat for Unit 1
  • · Manufactured and installed core parts of ST MSV and CV for Units 1 and 2
  • · Manufactured rotor and diaphragm stands for Units 1 and 2
  • · Produced key components for ST circulation pumps for Units 1 and 2
  • · Maintained HIP Casing and fixed bolts of MSV/CRV for Units 1 and 2
  • · Overhauled HP, IP Nozzle Boxes and Diaphragms for Units 1 to 3
  • · Overhauled MSV Strainers and Seats for Units 1 to 3
  • · Manufactured and replaced MSI Snout Pipes and Seal Rings for Units 1 to 4
  • · Replaced MSV/CV Seats and Bushings, RSV/ICV components for Units 1 to 4
  • · Manufactured and maintained CWP Assemblies for Units 1 to 6
  • · Overhauled small hydroelectric components for Units 1 to 6
  • · Produced MSV Pressure Seal Head and 3 other parts for Unit 3
  • · Manufactured and replaced CV Stand Bushing for Unit 3
  • · Repaired damaged LPSV Pressure Seal Head of BFPT(A) for Unit 3
  • · Maintained Main Disc and Pilot Valve Seats of MSV and ICV for Unit 3
  • · Straightened UP & LO Shaft Bending of circulating water pumps for Units 3 and 4
  • · Maintained HP/IP Outer/Inner Casing, Seal Ring, and Nozzle Box for Units 3 and 4
  • · Overhauled BFPT Diaphragm for Unit 3
  • · Disassembled and maintained Turning Gear for Unit 3
  • · Designed and manufactured L-0 and L-1 pressure reinforcement plates for Unit 3
  • · Manufactured CV Stand Sleeve for Unit 3
  • · Maintained Reject Ash Aeration Blower (Model-OCDL13) for Units 3 and 4
  • · Manufactured/replaced MSI Snout Pipe Seal Ring and maintained 1st Stage Pipe for Unit 4
  • · Produced LDP Stud Bolt and other components for Unit 4
  • · Maintained CBP Half Joint surface and Casing for Unit 4
  • · Manufactured pressure plate for Cross Over Pipe and maintained Air Compressor for Unit 4
  • · Overhauled MSV, CV, RSV, and ICV for Unit 4
  • · Overhauled CRV Strainer for Unit 4
  • · Maintained Nozzle Box, IP 1st-stage, and LP-A, B Diaphragm Partitions for Unit 4
  • · Manufactured and replaced ICV Upper Head Bushing and Seal Ring for Unit 4
  • · Manufactured and replaced CV Stand Bushing and Sleeve for Unit 4
  • · Manufactured and replaced MSV/RSV Pressure Seal Head Bushing and Seal Ring for Unit 4
  • · Manufactured IP Cooling Pipe for Units 5 and 6
  • · Overhauled old/new HP Nozzle Boxes for Unit 5
  • · On-site repair of cracked ICV Disc for Unit 5
  • · Manufactured and replaced MSV and CV Disc, Seat for Units 5 and 6
  • · Manufactured Gate and Main Rotor Shaft for Units 5 and 6
  • · Removed and disassembled seized Blades for Units 5 and 6
  • · Maintained Dice Pilot Valve Seat of ICV for Unit 6
  • · Replaced CV Lower Stand Bushing for Unit 6
  • · Overhauled Valves and Diaphragms for Unit 6
Korea South-East Power Co., Ltd. Samcheonpo Power Division
  • · Maintained erosion area of ST Inner Barrel for Unit 3
  • · Manufactured Hood Cir Gib Keys for ST LP TBN (A,B) for Units 3 and 4
  • · Overhauled ST Diaphragms for Units 3 to 5
  • · Maintained erosion area of ST BFPT Main Pump Inner Casing for Unit 3
  • · Maintained stuck bolts on ST HPSV for Unit 3
  • · Overhauled ST BFPT Barrel Shaft (Rotor Ass'y) for Unit 3
  • · Manufactured Major Valves for ST OH use for Units 3 and 4
  • · Maintained ST BFP Main Pump (B) Suction Cover for Units 3 and 4
  • · Manufactured ST CV Disc and inner parts for Unit 4
  • · Maintained ST BFPT (A,B) Pump Inner Casing for Unit 4
  • · Overhauled ST HP Inner Casing and manufactured MSI Snout Pipe for Unit 5
  • · Overhauled ST Nozzle Box for Unit 5
  • · Manufactured ST LP Hood Spray Nozzle and N2 Packing Ring for Unit 5
  • · Manufactured main steam valve components for ST Units 5 and 6
  • · Overhauled ST IP Diaphragm for Unit 6
  • · Maintained ST BFPT-B Diaphragm for Unit 6
  • · Manufactured ST Piston Ring for Unit 6
  • · Overhauled ST MSV Strainer for Unit 6
KOSPO Yeosu Thermal Power Plant Headquarters
  • · Manufactured and replaced ST MSV#1 Seat for Unit 1
  • · Maintained ST CV No.1 Connector Ass'y for Unit 1
  • · Manufactured ST Finger Pin for Unit 1
  • · Maintained ST Longitudinal Key and Bolt for Unit 1
  • · Manufactured ST CV Disc for Unit 4
  • · Maintained major components of ST MSV for Unit 4
KOSPO Goseong Green Power Headquarters
  • · Maintained ST BFPT Exhaust Duct for Unit 1
  • · Maintained ST BFPM Barrel Casing for Unit 1
  • · Manufactured ST Vapor Fan Flange for Unit 1
  • · Manufactured ST IP Diaphragm Radial Key and Support Plate for Unit 1
  • · Manufactured ST CVP Shaft for Unit 1
  • · Maintained ST BFPT-A Exhaust Duct and Thrust BRG Cover for Unit 2
  • · Maintained and disassembled ST MSV(RH) & CRV#1 Strainer for Unit 2
  • · Maintained ST CWP for Unit 2
  • · Maintained and disassembled ST MSV for Unit 2
KOSPO Gangneung Power Headquarters
  • · Improved ST BFP-T(A) Exhaust Duct for Unit 1
  • · Maintained ST CWP and COP for Unit 1
  • · Maintained ST N2 Packing Casing, IP, and LP Casing Bolts for Unit 1
  • · Maintained ST MSV Pressure Seal Head, Cap, and Spacer for Unit 1
KOSPO Yeongdong Eco Power Headquarters
  • · Manufactured and maintained ST MSV Pressure Seal Head and related components for Unit 1
  • · Removed and maintained ST Nozzle Box and IP Diaphragm for Unit 2
KOSPO Bundang Power Headquarters
  • · Manufactured and replaced ST HPSV Strainer for Unit 1
KOMIPO Boryeong Power Headquarters
  • · Fabricated/Replaced ST CV Diffuser for Unit 3
  • · Manufactured MSV#2 Valve components for Unit 5
  • · Supplied ST MSV By-Pass Valve for Unit 6
  • · Manufactured main steam valve components for Units 7 and 8
  • · Fabricated/Repaired ST MSI Snout Pipe for Units 7 and 8
  • · Manufactured ST CV Lever Pins and others for Units 7 and 8
  • · Fabricated Hex Head Socket Bolt for Unit 7
  • · Disassembled HIP Inner Casing for Unit 7 (Removed Snout Pipe & Seal Ring)
  • · Manufactured Nozzle Box Key for Unit 7
  • · Manufactured CV Push Rod Pin for Unit 7
  • · Manufactured CRV Stud Bolt for Unit 7
  • · Disassembled ST LP Diaphragm for Unit 7
  • · Replaced MSV, CV, CRV Seats for Unit 7
  • · Performed Seal Face maintenance on Feedwater Pump for Unit 7
  • · Maintained ST CRV Casing for Unit 7
  • · Manufactured Main Steam Pipe and valve components for Units 7 and 8
  • · Disassembled BFPT-A and B Diaphragms for Unit 8
  • · Manufactured LP Cross Over Pipe Bolt & Nut for Unit 8
KOMIPO Jeju Power Headquarters
  • · Fabricated/Replaced MSV & CRV Seats for Units 2 and 3
  • · Disassembled and maintained CV Chest for Unit 2
  • · Manufactured main steam valve components for Unit 2
  • · Disassembled Diaphragm for Unit 2
  • · Manufactured and maintained MSV, CV, IV, RSV parts for Unit 2
  • · Fabricated and maintained IP and LP Casing Bolts for Unit 2
  • · Manufactured MSV/CV Stem & Seat, CRV Seat for Unit 3
  • · Fabricated Cover Bolts for MSV/CV/CRV/IV for Unit 3
  • · Maintained ST Nozzle Box for Unit 3
  • · Emergency maintenance on IP Casing Bolt, Diaphragm, and Major Valve for Unit 3
KOMIPO Shinseocheon Power Headquarters
  • · Performed sectional maintenance on ST BFPT #B Exhaust Pipe for Unit 1
KOMIPO Sejong Power Headquarters
  • · Dismantled and maintained ST Diaphragm & Casing
KOMIPO Shin Boryeong Power Plant Division
  • · Manufactured and assembled ST Ventilator Valve Seat for Unit 1
  • · Repaired damaged Back Seat of ST MSV Pressure Seal Head for Unit 1
  • · Manufactured Balance Weight Holder Ass'y and LPBP Bonnet Stud Bolt & Washer for Unit 1
  • · Manufactured and assembled ST Valve Seat for Unit 1
  • · Manufactured ST MSV and CV components for Unit 1
  • · Manufactured ST Ventilator Valve for Unit 1
  • · Maintained ST CRV Strainer for Units 1 and 2
  • · Dismantled and maintained ST CV for Unit 2
  • · Manufactured ST LP Diaphragm stands for Units 1 and 2
KOWEPO Seo-Incheon Power Plant Division
  • · Manufactured ST Casing Bolts & Nuts for Unit 1
  • · Manufactured HP 2nd Stage Bucket & Cover for Unit 1
  • · Disassembled and assembled ST MSCV Seat for Unit 1
  • · Manufactured HP 2nd Stage Blades for Units 1 to 4
  • · Dismantled and maintained ST Diaphragms for Units 1 and 3 to 8
  • · Maintained ST MSV, RSV Strainers, and Bonnet for Units 1 and 6
  • · Dismantled and maintained ST MSV Seat for Unit 5
  • · Serviced ST N2 Packing Box (Upper/Lower) for Unit 8
  • · Maintained ST Nozzle Box
  • · Manufactured ST TBN Spill Strip and Packing Ring
  • · Manufactured ST LSB[A] TE Side Pressure Plate
  • · Manufactured ST Main Steam Valve parts
  • · Dismantled and maintained ST MSV, RSV Strainer, and Casing
  • · Manufactured ST HP MSI Snout Pipe
  • · Maintained ST BFPT Diaphragm & Casing
  • · Maintained boiler feedwater pump
  • · Maintained Air Compressor (A) MTR Base
  • · Maintained N2 Packing Seal Box / Manufactured N2 Packing Casing
KOWEPO Shin-Pyeongtaek Power Plant Division
  • · Manufactured ST Main Steam Valve parts
  • · Dismantled and maintained ST HPCV Disc & Stem Assembly
KOWEPO Taean Power Plant Division
  • · Dismantled and maintained MSV Strainer for Unit 1
  • · Dismantled and maintained HIP and LP Diaphragm for Units 1–4, 8–9
  • · Manufactured Casing Bolts & Nuts for Unit 1
  • · Manufactured HP 2nd Stage Bucket & Cover for Unit 1
  • · Maintained BFPT LP Control Valve for Unit 1
  • · Manufactured LPCV and Bypass Valves for Units 1–4
  • · Manufactured CV, MSV, and IV components for Unit 2
  • · Dismantled HIP Inner Casing and Turning Gear for Unit 2
  • · Dismantled and maintained MSV and CRV Strainers for Units 2–4, 7, 8
  • · Maintained N2 Packing Box and HP Casing for Unit 3
  • · Manufactured main steam valve parts for Unit 7
  • · Replaced CRV Head Cover Stud Bolt and CV Lower Bushing for Unit 7
  • · Outsourced overhaul of Inner Casing and Nozzle Box for Unit 8
  • · Manufactured Nozzle Box Gib Key, RSV Spacer Disc, Stem, and Seat for Unit 8
  • · Replaced RSV Seat for Unit 8
  • · Maintained Nozzle Box Joint Bolts and Diaphragm for Units 8, 9
  • · Repaired seized bolts on Outer Casing for Unit 8
  • · Manufactured and replaced CV Stand Bushing and LPBP SV #A-1 Disc for Unit 9
  • · Manufactured MSV and CV Seats and Bushings for Unit 9
  • · Manufactured HPCV and CV components for BFPT #A and #B for Unit 9
  • · Repaired seized bolts on Major Valve for Unit 9
  • · Manufactured and replaced MSV and CV Seats and Bushings for Units 9, 10
  • · Repaired crack damage on LP 18th Stage for Unit 10
  • · Manufactured and replaced CRV Bushings and MSV Cap Bolts for Unit 10
  • · Maintained LP 1st Stage Diaphragm for IGCC
KOWEPO Gunsan Power Plant Division
  • · Replaced and maintained HPSV (LH) Seat
  • · Maintained HP SV and CV Valve Seats
KOSPO Busan Thermal Power Plant
  • · Repaired RSV stem, nut, and pin for Unit 1
  • · 1st RSV CEOT spacer ring for Unit 1
  • · Manufactured CRV parts for Unit 1
  • · Repaired CV cross head and stem for Unit 1
  • · Maintained and removed MSV and CV stem for Unit 1
  • · Removed #2 MSCV upper head for Unit 2
  • · Removed MSCV balancing chamber and upper head bushings A and B for Unit 2
  • · Manufactured #2 SV coupling bolt for Unit 2
  • · Manufactured MSCV A and B CEOT rings for Unit 2
  • · Repaired CV cross head and stem pin hole for Unit 2
  • · Replaced main steam valve for Unit 2
  • · Repaired CV cross head & stem pin hole for Unit 2
  • · Manufactured CRV parts for Units 2 and 3
  • · Removed MSCV-A and B strainers for Unit 3
  • · Repaired seized MSCV stem for Unit 3
  • · CV cross head for Unit 3
  • · Repaired MSV stem pin hole for Unit 3
  • · Removed N1 and N3 packing casings for Unit 3
  • · Repaired CV disc assembly for Unit 3
  • · Removed MSV stem and MSV disc assembly for Unit 3
  • · Manufactured and repaired actuator valve nuts for MSV, RSV, and IV in Unit 3
  • · Manufactured MSCV spacers for Units 1 and 3
  • · Machined RSV stem nuts and pins for Units 3 and 4
  • · Manufactured and installed MSCVs for Units 2 to 4
  • · Replaced MSCV seats for main steam valves in Units 2 to 4
  • · Repaired cracks in the internal area of 3CC HRSG HP BCP for Units 3 and 4
  • · Removed MCV stem assembly for Unit 4
KOSPO Shin Incheon Power Division
  • · Maintained HIP and LP Diaphragms for Units 1 to 4
  • · Repaired damage on HIP Rotor Blade for Unit 1
  • · Manufactured N2 Packing Casing Gibs and Shims for Unit 1
  • · Overhauled CRV Strainer for Unit 2
  • · Replaced Support Bars N1 and N3 for Unit 3
  • · Replaced Zero Seal in N2 Packing Box for Unit 3
  • · Maintained N2 Packing Casing for Unit 3
  • · Maintained HIP TBN Casing for Unit 3
  • · Manufactured T-2 & T-3 Strainers for Unit 3
  • · Manufactured and installed CRV assemblies for Units 1 to 4
  • · Installed “Y” on Main & Reheat Steam Line for Units 1 to 4
  • · Installed Packing Box Support and Stoper B for Unit 4
  • · Replaced Zero Seal on N2 Packing for Unit 4
  • · Manufactured and installed MSCVs for Units 2 to 4
  • · Maintained CV Stem and Cross Head Ass'y for Unit 4
  • · Maintained MSCV-A and B Upper HEAD Bushings for Unit 4
  • · Replaced MSCV Balance Chamber for Unit 4
  • · Repaired stuck area on MSCV Stem for Unit 4
  • · Overhauled RSV Stem & Disc Ass'y for Unit 4
  • · Performed casing maintenance for GT Units 3 and 4
KOSPO Hadong Power Division
  • · Manufactured Ventilator Valve Spring for Unit 1
  • · Maintained Cover Gland Bushing Assembly for Unit 1
  • · Manufactured LPBP Gland Bushing for Unit 1
  • · Maintained and overhauled MSV Strainer and Bushing for Unit 1
  • · Manufactured and overhauled Ventilator Valve for Unit 1
  • · Replaced TCV Seat for Unit 1
  • · Manufactured Soot Blower DRN Valve Stem & Bushing for Unit 1
  • · Manufactured LP Guide Bushing for Unit 1
  • · Improved MSV Head Cover Bolt fastening for Units 1 to 6
  • · Manufactured Nozzle Box Shim Plate and MSV#2 Bypass Valve for Unit 2
  • · Manufactured LPBP Guide Bushing for Unit 2
  • · Maintained damaged LPBP SV Stem, SV, CV Bonnet & Cover for Unit 2
  • · Performed field maintenance to remove stuck bolts on Nozzle Box for Unit 2
  • · Maintained BFPT-B Casing Seal Face for Unit 2
  • · Maintained damaged LP A,B Casing Flange surfaces for Unit 2
  • · Manufactured MSV#2 Stud Bolt and Gland Bushing for Unit 2
  • · Manufactured and replaced BFPT HPCV Bushing for Unit 2
  • · Replaced Disc Bushing and manufactured Main Steam Valve parts for Unit 2
  • · Maintained damaged LP A,B Inner Casing Flange surfaces for Unit 3
  • · Maintained stuck bolts on HIP Casing for Unit 3
  • · Maintained eroded areas of HIP Casing (U/H & L/H) for Unit 3
  • · Maintained LP Inner Casing Shield Cover Bolt Hole for Unit 3
  • · Manufactured Grove Valve Bonnet Bush for Unit 3
  • · Manufactured HP Control Valve Stem & Disc Ass'y for Unit 3
  • · Overhauled BFPT Diaphragm for Units 3 to 7
  • · Manufactured Main Steam Valve parts for Units 3 to 5
  • · Overhauled MSV#2 Disc Bushing for Unit 4
  • · Manufactured/replaced Main Steam Valve parts for Unit 4
  • · Overhauled LP-A Diaphragm on GE side for Unit 5
  • · Replaced CV Sleeve and MSV #2 Bushing for Unit 5
  • · Manufactured MSV #1,2 Body Bolt for Unit 5
  • · Maintained RSV PSH internal Bushing and Seal Ring for Unit 5
  • · Manufactured TBN Nozzle Box Snout Ring for Unit 5
  • · Maintained LP Inner Casing Shield Cover Bolt Hole for Unit 5
  • · Manufactured Piston Ring for Units 3 and 5
  • · Maintained eroded HIP Inner Casing for Unit 5
  • · Maintained stuck bolts for Units 5 to 8
  • · Overhauled L-1 Stage Diaphragm for Units 4 to 9
  • · Maintained Turning Gear for Unit 6
  • · Emergency repair of HIP Casing Snout Pipe and Sealing Ring for Units 7 to 8
  • · Overhauled Nozzle Box for Unit 7
KOSPO Samcheok Power Division
  • · Manufactured Balance Weight and LP Bypass Ring for Unit 1
  • · Manufactured HPBP Valve Stem Guide Bushing for Unit 1
  • · Maintained HP SV Guide Bushing & Cover for Unit 1
  • · Maintained LP Gland Packing Casing for Unit 1
  • · Repaired damaged area of IP Upper Casing for Unit 1
  • · Maintained MSV Coupling Spacer for Unit 1
  • · Maintained N2 Packing Casing for Unit 1
  • · Maintained Diaphragm for Unit 1
  • · Maintained BFP-T Vapor Extractor Hub for Unit 2
  • · Inspected and manufactured CV Disc & Arm, and MSV Pin hole for Unit 2
  • · Maintained LP Gland Packing Casing for Unit 2
KOSPO Namjeju Power Division
  • · Maintained ST HIP Casing, RSV RH & LH
  • · Repaired bolt holes of lower blade ring and HP Dummy Ring
  • · Repaired fractured and stuck bolts of ST Gland Packing
  • · Maintained Bearing Cover and Thrust Bearing Shim
  • · On-site maintenance of ST N1-Lower Gland Packing Casing
  • · Manufactured parts for MSV, GV, and RSV assemblies
  • · Disassembled and maintained RSV RH and GV
KOSPO Yeongnam Power Division
  • · Manufactured ST IPSV Spring Box, HPSV parts, and Bonnet Guide Bushing
  • · Manufactured parts for ST IPCV Pilot Valve
  • · Maintained ST CWP Assembly
  • · Manufactured ST HIP Casing, HIP Blade Ring, and Shield
  • · Disassembled and maintained ST LP1st-stage Diaphragm and Dummy Ring
  • · Maintained ST Blade Ring Liner
  • · Repaired ST LP1st-stage Groove
  • · Manufactured and replaced ST HPSV and HPCV parts
EWP Dangjin Power Division
  • · Manufactured MSV #2 Disc and Bushing for Units 1–4
  • · Maintained Nozzle Boxes for Units 2, 5, and 6
  • · Maintained Diaphragms for Units 2, 3, 6, and 8
  • · Maintained IV Disc and EV Bonnet Bolt for Unit 3
  • · Maintained LP Gland Packing Casing for Unit 3
  • · Maintained Snout Pipes for Units 5, 6, and 8
  • · Maintained MSV#2 Disc & Stem Ass'y for Unit 5
  • · Manufactured Main Steam Valves for Units 5 to 7
  • · Manufactured 11 types including Pin and Washer for Unit 5
  • · Maintained HIP Upper Inner/Upper Casing for Unit 6
  • · Maintained Nozzle Box for Unit 6
  • · Maintained BFPT 4th-stage Upper Diaphragm for Unit 6
  • · Maintained stuck bolts on HIP Outer Casing for Unit 6
  • · Tapped HIP Inner Casing Lower Bolt Holes for Unit 6
  • · Removed stuck bolts and conducted size-up work on MSV Casing for Unit 6
  • · Maintained Diaphragms for Units 7 and 8
  • · Manufactured Inner/Outer Sealing and Locking Ring for HP Casing for Unit 8
  • · Manufactured bolts and nuts for HIP Upper Casing for Unit 8
  • · Manufactured bolts and nuts for N1,3 Packing Casing for Unit 8
  • · Manufactured Gib Key for Nozzle Box for Unit 8
  • · Removed and manufactured bolts at TC Assembly area for HIP and LP Casings for Units 7 to 9
EWP Honam Power Division
  • · Performed blasting and bonnet maintenance on ST MSV Strainer for Unit 6
EWP Ulsan Power Division
  • · Removed and maintained ST Upper Diaphragm for Unit 3
  • · Replaced ST HPCV Pilot Valve for Unit 3
  • · Replaced ST HPSV Bonnet Lower Bushing for Unit 4
EWP Ilsan Power Division
  • · Repaired crack in ST LP Diaphragm
  • · Maintained ST 2CC HPCV
EWP Donghae Bio Power Division
  • · Supplied spare parts for circulating water pump maintenance for ST Units 1 and 2
  • · Maintained ST CWP and COP for Units 1 and 2
EWP Donghae Power Division
  • · Removed and maintained ST CWP spider, shaft, and related components for Units 1 and 2
EWP Pyeongtaek Power Division
  • · Removed and maintained ST PSV bearing support
  • · Manufactured ST A01 bearing
Korea Hydro & Nuclear Power
Korea Hydro & Nuclear Power Co., Ltd. Hanbit Nuclear Power Plant
  • · Maintained sealing area of HP Outer Cylinder for Unit 1
  • · Maintained Gland-Seal Ring Retainer of LP Turbine A for Unit 1
  • · Maintained Diaphragm of Main Feed Water Pump (MFWP) for Unit 1
  • · Developed WPS for MFWP Turbine Diaphragm for Unit 1
  • · Removed and maintained HP Diaphragm for Unit 1
  • · Removed and maintained MFWP Casing & Diaphragm for Unit 1
  • · Maintained GSE141F1 filter assembly surface for Units 1 and 3
  • · Removed and maintained Rotor Stand for Units 1 and 4
  • · Maintained Upper Head of LP combined intermediate valve for Units 3 and 4
  • · Manufactured and installed vibration/stress test equipment for LP turbine final stage blades
  • · Manufactured MOP Seal & Wear Ring for turbine
  • · Maintained plug and seat ring for FC-UV008
  • · Maintained high-pressure control valve of main feedwater turbine
  • · Maintained LP Gland Seal Ring Retainer
  • · On-site maintenance of GE-side Lower Diaphragm in Unit 6 LP-C
  • · Removed and maintained Main Pump Diaphragm & Nozzle Box for Unit 6
Korea Hydro & Nuclear Power Co., Ltd. Kori Nuclear Power Plant
  • · Manufactured HP Casing Seal Key and Spring for Unit 3
Korea Hydro & Nuclear Power Co., Ltd. Hanul Nuclear Power Plant
  • · Maintained and disassembled ST Rotor Stand for Units 1 and 2
  • · Maintained LP “A” Diaphragm for Unit 4
  • · Disassembled Main Pump Casing & Diaphragm for Units 5 and 6
GE
  • · Maintained HP 1st stage Bucket Root pin for Hanbit Unit #1
  • · Disassembled HIP Casing and maintained MSV/CV Seat for POSCO Pohang Units 5–6
  • · Maintained MSV Header for POSCO Pohang Unit 5
  • · Disassembled HP & LP Upper/Lower Casing for POSCO Pohang Units 7–8
  • · Manufactured fixing Bolts & Nuts for ST Boring Machine at POSCO Pohang Unit 8
  • · Replaced ST CV Seat for POSCO Pohang Unit 8
  • · Adjusted Packing Head of ST1 at POSCO Pohang
  • · Repaired crack on ST HP Lower Casing at POSCO Pohang
  • · Supplied 5 types of consumable welding materials for POSCO Pohang
POSCO Co., Ltd.
POSCO Co., Ltd. Gwangyang Steel Works
  • · Disassembled ST MSV
  • · Disassembled ST MSV, GV, and MSCV Upper Head for Unit 1
  • · Manufactured MSV and GV Valve components for Units 1–8
  • · Disassembled MSV and GV Valves for Units 1, 3, and 4 (By-product Gas Power)
  • · Repaired HP Upper Casing crack and H/J surface for Unit 1
  • · Manufactured and maintained boiler safety valve Disc
  • · Localized development of ST IP 1st & 2nd Blade
  • · Disassembled ST TBN Diaphragm
  • · Disassembled ST MSV Stem & Disc Ass'y and Strainer
  • · Maintained ST TBN Diaphragm & Rotor
  • · Disassembled ST 2CDQ Steam Turbine rotating blades
  • · Manufactured L.O Pump Guide and Seal Ring
  • · Manufactured RSV Disc and other components for Unit 2
  • · Restored main steam valve performance for Units 2–4
  • · Disassembled MSV Bonnet of main steam valve for Units 2, 5–8
  • · Replaced MSV Seat on main steam valve for Unit 6
  • · Maintained ST HP Casing Bolts for Unit 7
Siemens
SK Hynix Icheon Power Plant
  • · Disassembled ST HIP Outer Casing
  • · Maintained ST Sealing Segment
SK Hynix Cheongju Power Plant
  • · Disassembled ST HIP Outer Casing (Lower & Upper)
  • · Maintained ST Seal Ring Segment
  • · Maintained Lower Nozzle of ST HIP Outer Casing
  • · Repaired ST Rotor
  • · Maintained ST HIP Inner Casing, L-Ring & Thread Ring
SK Hynix Yeoju Power Plant
  • · Disassembled ST HIP Outer Casing (Lower & Upper)
  • · Maintained ST Sealing Segment
Gwangyang SK E&S
  • · Disassembled ST IP, HIP Diaphragm, and Gland Packing for maintenance
  • · Maintained ST MCV & CRV Valve Seat
  • · Manufactured internal parts for ST CMV and CRV
  • · Maintained ST CMV and CRV Seat and Upper Head
  • · Disassembled ST Rotor Support Block and Gland Packing
  • · Replaced ST RSV Actuator Union
  • · Replaced ST CMV-A Sealing Ring
  • · Maintained ST HP Diaphragm
Dongducheon Dream Power Co., Ltd.
  • · Reconditioned 2nd-stage Rotor Assy of fuel gas compressor
  • · Manufactured main steam valve parts for ST Units 1 and 2
  • · Manufactured ST IPSV Bushing, LVDT LOD, COP Impeller Balancing, and Hex Nuts for Unit 1
  • · Repaired erosion damage on IPCV Seat (Blocks 1 and 2) for ST Units 1 and 2
  • · Maintained and replaced ST HPSV and IPCV Bushing for Unit 2
  • · Manufactured ST FGC Main Shaft Assy and reconditioned outer housing of gearbox for Unit 2
  • · Fabricated jig for disassembly of multistage pressure reducing valve
  • · Balanced Stage 1 Rotor of ST FGC
  • · Maintained ST IPCV Valve Disc
  • · Disassembled ST COP and CWP for maintenance
Pocheon Power
  • · Machined the steam inlet pipe face of HP casing for ST Unit 1
  • · Planned B/L maintenance for Unit 2 (including Tad Stud Bolts)
  • · Maintained ST Bypass Ventilator Valve for Unit 2
  • · Manufactured spare parts for ST MSCV & BVV maintenance on Unit 2
GS Pocheon Green Energy
  • · ST HPCV Seat Manufacturing and Assembly
  • · ST LP Rotor Stand Manufacturing
Korea Electric Power Corporation Research Institute
  • · Rotor Bending Correction Device Process Development
  • · Bucket Cover Welding Validation Testing and Demonstration Bucket Cover Welding Maintenance Technology Development
  • · ST Spin Tester Manufacturing
KEPCO KPS Co., Ltd.
  • · Sudan KNPS #3,4 S/T Carrier Maintenance
GS Donghae Power Co., Ltd.
  • · Manufactured HPU oil transfer tank
  • · Manufactured and maintained ST CWP shaft & impeller
  • · Constructed ST CWP-D motor pedestal
  • · Maintained ST CV & OLV components
  • · Removed stuck bolts on ST
  • · Corrected shaft bending on small hydro turbine
  • · Maintained ST CVP heat exchanger
  • · Manufactured and replaced ST CWP impeller ring
  • · Overhauled ST butterfly valve
Suwan Energy
  • · ST MSV, GOV Removal Maintenance
  • · ST HP Casing Removal Maintenance
  • · ST GV Piston Ring Manufacturing
GS Power Anyang
  • · Manufactured and maintained ST MSV & CV components
  • · Machined ST IP casing pin hole and overhauled packing casing
Goseong GGP
  • · Removed and re-tapped stuck bolts of ST Unit 1
  • · Maintained stuck bolts on ST Unit 2 NO.3 Bearing Cover
Daeryun Power Co., Ltd.
  • · Generator Maintenance Equipment (Rotor Stand, etc.) Manufacturing
  • · ST MSV Stem & Nut Pin Hole Maintenance
  • · ST Main Steam Valve Internal Part Components Manufacturing
CGN Yulchon Power
  • · ST HPSV Bushing Manufacturing Replacement Maintenance, etc.
Seoul Energy Corporation (Nowon Cogeneration)
  • · ST Bolt Manufacturing
Lotte Chemical Co., Ltd. Daesan
  • · A105-JDT Turbine Rotor Maintenance
  • · A105-JDT Turbine Shaft Manufacturing
  • · NC 108-JAT Turbine Rotor Maintenance
BHI(POSCO Pohang#7)
  • · Maintained ST LP Casing V/J surface for POSCO Pohang Unit 7
Hyundai Engineering & Construction Co., Ltd.
  • · Vietnam Mong Duong 2 HIP TBN Casing Stuck Bolt Maintenance
Hyundai Heavy Industries Co., Ltd.
  • · Turbine Generator Overhaul Maintenance
Daedong IM Co., Ltd.
  • · Sudan KNPS PH1 TBN Last Blade Manufacturing
Busan Fashion Center
  • · Turbine Rotor & Carrier Blade New Manufacturing and Replacement
  • · Gear Unit Maintenance
Byeollae Energy
  • · ST HP 3rd Stage Blade and Diaphragm Maintenance
Korea Plant Service
  • · Performed ST HIP Rotor Blanding for Rabigh Unit 2
Gimhae Incineration Plant
  • · Manufactured ST Turbine Blade & Disc